Friday 19 December 2008

Nestle Purina - Sudbury
Supplied our type SC constant wattage heating tape.

Wednesday 17 December 2008

Harrogate South WWTW
ESH were contracted to replace the old trace heating and thermal insulation with new and to also provide frost protection to the 2" Ø new pipework.

Friday 12 December 2008

Doncaster WWTW
For this project ESH supplied and installed trace heating and thermal insulation to provide frost protection to the 1" Ø Salt Saturates pipework and also the Lamella Feed pipework.

Thursday 11 December 2008

Oasis Academy - Immingham


Designed, supplied and installed 21 Trace Heated step panels for an external stair case. Internally we also supplied and installed a hot water maintenance system on the DHWS pipework which required 1600m of H2OWAT55 tape.

Tuesday 9 December 2008

Seacroft Hospital - Leeds
To design, supply materials and labour to install the trace heating system to provide frost protection to four 25mm Ø flexible hose's & 32mm Ø plastic pipework.

Friday 5 December 2008

Stepan (UK) Ltd - Cheshire
175m of trace heating was supplied and installed to temperature maintain pipework at +42°C in the Blow head area.

Tuesday 2 December 2008

International Logging Technology Ltd - Plymouth
Designed and supplied the materials to temperature maintain a plastic hose at +20°C in a minimum ambient of -40°C in a Gas Group IIB, Classification T3 Hazardous Area.

Friday 28 November 2008

Derby STW
Designed, supplied materials and labour to install frost protection to a Condensate Pot - 900mm dia x 1750mm tall.

Wednesday 26 November 2008

Wootton Place - Oxon
Wootton Place is an exclusive private development of 13 luxury houses. Here we supplied and installed 153m of H2OWAT55 heating tape, to temperature maintain flow pipework carrying domestic hot water to Douches.

Tuesday 25 November 2008

Pure Office Building - Swindon
For this new office development, ESH supplied and installed trace heating to temperature maintain pipework carrying domestic hot water at +55°C. 129m of heating tape required in total.

Monday 24 November 2008

Esholt WWTW - Bradford
Supplied Hazardous Area trace heating cable and thermostats to this project.

Friday 21 November 2008

Warburtons Bakery
Supplied Warburtons with our type VC constant wattage heating tape.

Thursday 20 November 2008

Calthorpe House - Edgbaston 

Within this prestigious 107,044 sq ft office accommodation, ESH frost protected external pipework against minimum ambient temperatures of -15 degrees C. Overall 600m of FBTOJ heating tape was used.

http://www.traceheatingdirect.com/self-regulating-heating-tapes.html
UBHT Hospital - Bristol
The project scope was to supply and install trace heating to frost protect the following metal pipework: 

  • 8th floor - 54m of CHW pipework
  • 9th floor - 45m of CHW pipework
  • 9th florr - 20m of MCW pipe
  • 9th floor - 10m of condensate pipe
  • Riser - 40m of MCW pipe

Wednesday 19 November 2008

Lownethwaite WTW - Richmond 
ESH supplied and installed frost protection trace heating to 90m of metal pipework.
Chester WWTW
Supplied and installed trace heating to 80m of metal washwater pipework using type VC constant wattage heating tape.

Tuesday 18 November 2008

Complete Energy System - Cheshire
Supply materials and labour to complete the installation and commissioning of self regulating frost protection trace heating on the cold water supply pipework.

Friday 14 November 2008

Northampton Museum & Art Gallery
Supplied materials and labour to install and commission trace heating to frost protect pipework associated with two chillers on the roof of the building.

Wednesday 12 November 2008

The Heights - Brookland
Within this prestigious commercial office development, ESH supplied and installed 120m of type VC constant wattage trace heating tape, to provide frost protection.

Tuesday 11 November 2008

Filpumps Ltd - Aberdeenshire 
Supplied 580m of type VC constant wattage heating cable.
Didcot Rail Centre
Designed, supplied materials and labour to install and commission trace heating to frost protect pipework associated with 3 chillers and 4 AHU's. Overall 330m of type VC heating tape was required.
Marks & Spencers - Luton Arndale Centre
For this new Marks & Spencers store, ESH supplied and installed trace heating to frost protect the following pipework: 

  • 45m of MCWS in the external basement loading bay area
  • 229m of heating pipework on the roof, with connections to three air handling units
  • 25m of MCWS in the internal loading bay area

Monday 10 November 2008

Unipet International Ltd - Kent
Type SC constant wattage heating cable was installed onto the beef fat pipework to maintain the temperature above +55°C. The pipework run both internal and external of the building with varying minimum ambient temperatures.

Friday 7 November 2008

Marstons Brewery - Burton On Trent
Supply materials and labour to install and commission a trace heating system to maintain a temperature of +30°C on grain pipework in a minimum ambient of -15°C.

Thursday 6 November 2008

Headrow Building - Leeds
300m of type VCB constant wattage trace heating tape was supplied and installed to frost protect the CHWS & LTHWS pipework. Also 50m of FBT self regulating tape was supplied and installed onto the 6" sprinkler pipework to provide frost protection.

Monday 3 November 2008

Omya UK Ltd - Melton
A trace heating system was supplied and install to provide frost protection to the 4" Ø pipework.

Wednesday 22 October 2008

Mythe Water Treatment Works
For our second visit to this site, ESH supplied and installed frost protection trace heating for the Surge tank and associated pipework.

Tuesday 14 October 2008

Seedy Mill WTW - Lichfield
To design, supply materials and labour to install both trace heating and thermal insulation to provide temperature maintenance at +15°C for plastic dosing pipework.

Thursday 9 October 2008

Nottingham University - Maths & Physics Building
Type ESRS self limiting heating tape was supplied and installed to provide frost protection to a small length of external pipework.

Monday 6 October 2008

Whitlingham WWTW
Supplied and installed trace heating to frost protect the following: 

  • Cambi plant - two effluent pipe runs
  • Sludge transfer pipework
  • Contact tank infill and SAS pipework
  • Contact tank mixer pump station
  • Thickened SAS transfer pump station pipework
  • Strain press pipework

Friday 3 October 2008

Sentrum - Woking 
To supply materials and labour to install and commission trace heating to provide frost protection to the external chilled water pipework, this also included 16m of 100mm/200mm pipework in each of the 3 McQuay chiller units.

Thursday 2 October 2008

Network Rail - Guildford 
Supplied 480m of type VC constant wattage heating tape to this project.

Thursday 25 September 2008

British Nuclear Fuels - Salwick
ESH designed and supplied 8 x heated jackets and 1 heated hose to maintain the pipework system at +100°C.

Tuesday 16 September 2008

Tesco Supermarket - Hartlepool
Supplied type VC constant wattage heating tape for the prevention of frost formation within the supermarkets sprinkler system.

Thursday 11 September 2008

Market Hall - Bolton
Our second project here, consisted of ESH supplying and installing frost protection to the markets sprinkler pipework.

Friday 5 September 2008

Arla Foods Limited - Settle
Provided temperature maintenance at +20°C to approximately 25m of 1.5" NB plastic pipe containing caustic soda. Supply and install.

Wednesday 3 September 2008

Premier Foods - Nottingham 
Supplied materials and labour to install our type H2OWAT65 self limiting heating tape, to provide temperature maintenance of +65°C.

Friday 29 August 2008

Hilton Hotel - Manchester Airport
ESH were contracted to inspect and test the existing trace heating system and advised accordingly.

Wednesday 27 August 2008

Marks & Spencers - Worcester 
ESH supplied, installed and commissioned trace heating to frost protect the LTHW pipework: four sets of metal pipe up to 48mm OD, flow and return, 44m in all.

Tuesday 19 August 2008

Andrew Corporation - USA
Designed and supplied 32 x 3.7m dish heater panels to fit to the rear of Satellite Receiving Dish Aerials to prevent ice formation.

Thursday 14 August 2008

Temple Moor High School - Leeds
To supply materials and labour to install a trace heating system to provide frost protection to the AHU pipework mounted on the roof area.

Tuesday 12 August 2008

Ashford WWTW
For this project the Sodium Hydroxide pipework needed to maintain a temperature of +20°C in a minimum ambient of -15°C. ESH supplied and installed 105m of type FBTBOJ self regulating heating tape to complete the job.

Monday 11 August 2008

Wintringham Academy - Grimsby
Type H2OWAT55 self limiting heating tape was supplied and installed onto the HWS pipework in order to maintain the pipe temperature at +55°C.
Forbes Technologies Ltd - Kelso
Designed, supplied and installed a trace heating system to temperature maintain a large tank 3.05m Ø X 3.79m high and the associated pipework, at +30°C.

Friday 8 August 2008

Bulmers Cider Company - Hereford
ESH supplied 220m of type VC constant wattage trace heating cable, for installation onto the sprinkler system to provide frost protection.

Wednesday 6 August 2008

Budds Farm WTW - Havant
ESH supplied 100m of type FBTBOJ self limiting heating tape to this project.

Thursday 31 July 2008

St Helens College 
To supply, install and test electrical trace heating for frost protection of the hot temperature water pipework to two off AHU's on the roof area.

Thursday 24 July 2008

Eltherm - Germany
Supplied Eltherm with 11,000m of VCBOJ constant wattage heating tape.

Tuesday 15 July 2008

Witney STW
For this our second project at Witney STW, ESH supplied and installed trace heating to frost protect at +5°C in a minimum ambient of -15°C:

  • 22m of pipework in area of Spirac and Alfa Laval machines
  • 13m of pipework serving the Combi Wash in the Inlet Area
  • 26m of pipework serving thr three inlet screens

Friday 4 July 2008

Toyota Motor Manufacturing - Flintshire
The project scope was to supply materials and labour to install trace heating and thermal insulation in order to temperature maintain mild steel pipework at +60°C.

Wednesday 2 July 2008

Churchill Hospital - Oxford
The project scope was to supply and install trace heating to: 

  • Temperature maintain the roof mounted Light Grade Fuel Oil pipework at +15C
  • Frost protect the roof mounted steel CHW pipework
  • Frost protect 22mm copper BCWS pipework associated with the LINNARK area

Friday 27 June 2008

Dairy Crest - Nuneaton
Supplied and installed trace heating to frost protect the following pipework: 

  • 34m of MCWS and 27m of heating pipework on the roof area
  • 35m of MCWS pipework from the high level plant room to a drench shower and wash down tap in the loading bay/skip area
  • 15m of MCWS incoming mains to a drench shower in the ground floor plant room area

Thursday 26 June 2008

Market Hall - Bolton
Scope of work was to supply and install the electrical trace heating to provide frost protection to the condenser pipework and the cold water services (flow and return) pipework, all situated on the roof area.

Wednesday 25 June 2008

Rochdale WWTW
The project scope was to design and supply materials and labour to install trace heating and thermal insulation to both steel and plastic pipework, to provide frost protection.

Tuesday 24 June 2008

Soseki Japanese Restaurant - London 
ESH supplied and installed 70m of type H2OWAT55 self limiting heating tape, to maintain the DHWS pipework at +55°C in an ambient of +18°C.

Monday 23 June 2008

Cantor Building - Sheffield Hallam University 
The Cantor building on Furnival Street houses elements of the Faculty of Arts, Computing, Engineering and Sciences, as well as other campus facilities. For the large scale project ESH supplied and installed trace heating to provide frost protection to the exposed CTH, CHW & MCW service pipework.

Friday 20 June 2008

Royal Naval Air Station - Culdrose
To design and supply materials and labour to install and commission trace heating to provide frost protection to the 6" Ø steel pipework.

Thursday 19 June 2008

IBIS Hotel - Birmingham
ESH designed, supplied, installed and commissioned a trace heating system to provide frost protection to the chilled water pipework (flow and return) and cold water service pipework. In total 142m of pipework in five runs, three on the hotels roof.

Wednesday 18 June 2008

Netstore Plc - Reading
For this project ESH were contracted to supply materials and labour to install a trace heating system to frost protect 1500mm NB pipework.

Tuesday 17 June 2008

Burnley WWTW
ESH supplied and installed an additional 90m of type FBTBOJ self limiting tape to this ongoing project.

Wednesday 11 June 2008

Tessenderlo Fine Chemicals Ltd - Leek
Designed and supplied a trace heating system to be applied onto a tank 2.95m Ø x 2.1m high, in a Zone 1 Gas Group 11b Classification T3 electrically Hazardous Environment.

Monday 9 June 2008

Oasis Academy - Immingham
1600m of type H2OWAT55 self regulating heating tape was supplied, installed and commissioned to maintain the DHWS pipework at +55°C.

Thursday 5 June 2008

Boots Opticians - Higher Chelmer Shopping Centre
ESH supplied and installed 75m of H2OWAT55 to temperature maintain the HWS pipework at 55°C.

Tuesday 3 June 2008

University Of Sheffield - Music Practice Facility
The scope of work was to design, supply and install a trace heating system to maintain the DHWS pipework temperature at +55°C and periodically purge the system to a temperature of 65°C.

Monday 2 June 2008

Audi Showroom - Sheffield 
162m of pipework in the basement area was trace heated to provide frost protection in a minimum ambient temperature of -15°C. ESH supplied and installed type VC constant wattage heating tape.

Friday 30 May 2008

Manchester Joint Hospital
ESH supplied and installed the trace heating system to provide frost protection to the chilled water supply: 200m in phase 1, 90m in phase 2, 180m in phase 3.

Thursday 29 May 2008

Mythe Water Treatment Works
To supply and install trace heating to temperature maintain a vessel containing Caustic Soda at +15°C. The existing circuits were removed before the new trace heating was installed.

Wednesday 28 May 2008

Rosemont Pharmaceuticals - Leeds
To design, supply materials and labour to install trace heating to provide frost protection to the chilled water services pipework and to temperature maintain the DHWS pipework at +65°C.

Monday 26 May 2008

Derby STW
ESH went back to Derby STW to install an additional 35m of VC constant wattage heating tape, to frost protect the wash water pipework.

Monday 19 May 2008

Debenhams - White City
The project scope here was to supply labour and materials to install and commission the following trace heating: 

  • Frost protection to 66m of roof mounted flow and return copper MCW pipework
  • Temperature maintenance at 55°C of 134m of domestic hot water service pipework

Friday 16 May 2008

Marks & Spencers - White City
920m of VC constant wattage trace heating tape was supplied and installed to provide frost protection to the CHWS & HWS pipework.

Wednesday 14 May 2008

Sterecycle Ltd - Rotherham
ESH were contracted to design, supply and install electric trace heating for frost protection to the mild steel TCWS pipework.

Monday 12 May 2008

Novotel Building - Paddington



1300m of Trace Heating was used on the pipework to maintain the temperature at 55 degrees C for both internal and external HWS pipework. Also frost protected the roof area cold water and heating pipework. ESH supplied and installed the work.

Friday 9 May 2008

Manchester Academy
To supply and install trace heating to provide frost protection to the copper BCWS pipework on the Academy's roof.

Friday 2 May 2008

Paradise Street Development - Liverpool
One of our largest projects up at this site involved us suppling and installing trace heating to frost protect copper pipework in the following areas: 

  • Pipework form main sprinkler tank room to kiosk
  • Five kiosk pipes in the service corridor
  • Landlords BCWS to cleaners sink
  • 40m tee to bib taps. 
In total this required 340m of FBTBOJ heating tape.

Thursday 1 May 2008

Burnley WWTW 
The project scope was to supply and install electric trace heating to provide frost protection to 140m of external pipework.

Wednesday 30 April 2008

Birch Coppice Ind. Estate - Tamworth
We supplied labour and materials to temperature maintain the indoor domestic hot water service pipework at +55°C.

Thursday 24 April 2008

Sentrum - Watford
Supplied materials and labour to install and commission trace heating to protect the pipes from freezing in a minimum ambient of -15°C.

Wednesday 23 April 2008

Dakota Hotel - Farnborough 
ESH supplied the trace heating to frost protect the external pipework.

Monday 21 April 2008

Rhodia UK Limited - Hounslow 
To supply labour and materials to install and commission a trace heating system using our type TF constant wattage heating tape which has a Teflon sheath.

Friday 18 April 2008

The Premier Inn - Barking
Supplied the materials to be used for a temperature maintenance system.

Wednesday 16 April 2008

John Lewis Store - The Shires Centre
Supplied our type ESRSBOJ self regulating heating tape to this project.

Tuesday 15 April 2008

ITT Advanced Water Treatment - Pitstone 
Supplied 300m of type SC constant wattage heating tape to this job.

Friday 11 April 2008

Emirates Link Reslab LLC - Abu Dhabi
ESH designed and manufactured 5 x heating jackets 300mm long, 500mm int dia.

Tuesday 8 April 2008

Malvern STW
For this project ESH supplied 250m of type ESRSBOJ self limiting heating tape.

Monday 7 April 2008

ABB Ltd - Telford
For this local project ESH supplied and installed both the trace heating and thermal insulation to frost protect a 2" stainless steel pipe line.

Wednesday 2 April 2008

Deutsche Bank - Watford
For this large project, ESH designed, supplied materials and labour to install and commission trace heating to provide frost protection to the chilled water pipework and 6 buffer vessels, all external roof mounted in a minimum ambient temperature of -15C. In total this project required 3371m of type VC constant wattage heating tape.

http://www.traceheatingdirect.com/constant-wattage-parallel-circuit/constant-wattage-heating-tape-type-vcb.html

Tuesday 1 April 2008

Nova Laboratories Ltd - Leicester 
ESH supplied 280m of constant wattage heating tape to this project.

Wednesday 19 March 2008

Paradise Street Development - Liverpool
For this project ESH supplied and installed trace heating to provide frost protection to 50m of 22mm Ø copper pipework to a bib tap.

Thursday 13 March 2008

Poaka Beck WTW - Cumbria
Supplied, installed and commissioned the trace heating system to proved frost protection to the following areas: Lamella Plant, Uncontaminated pump station, Dirty washwater balance tank, Interstage pump station, Air blower drain lines and the Feed pump station.

Tuesday 11 March 2008

Trox (UK) Ltd - Norfolk
ESH designed and manufactured 10 x heating panels 440 watts 240v c/w with earth screen.

Thursday 6 March 2008

Calsonic Kansei - Tyne & Wear
ESH designed and manufactured 2 x IBC heating jackets 100w 240v c/w complete with thermostatic control.

Wednesday 5 March 2008

Derby STW 
60m of type FBTBOJ self regulating heating tape was supplied and installed onto both steel and plastic pipework to provide frost protection.

Friday 29 February 2008

Direct Table Foods - Bury St Edmunds 
Supplied additional materials and labour to rearrange and extend the original trace heating system.

Tuesday 26 February 2008

TK Maxx Store - Humberstone Gate
ESH supplied and installed the hot water trace heating system to be maintained at +55°C. All pipework was indoors and fitted with our H2OWAT55 self limited heating tape.

Monday 25 February 2008

Motney Hill STW - Kent
Supply only, 150m of FBT self regulating trace heating tape.

Thursday 21 February 2008

Kings Lynn STW - Norfolk
ESH were contracted to supply and install an additional 306m of VC constant wattage heating tape to vairous different pipeworks within this site.

Tuesday 19 February 2008

Banwell WTW
Supplied materials and labour to install and commission trace heating to frost protect the following areas: 

  • Membrane building area
  • PAC/Sulphuric acid area
  • Phosphoric acid area
  • Booster pump kiosk

Monday 18 February 2008

Marks & Spencer Stores
ESH supplied and installed two new M&S stores - Luton Arndale Centre & White City London, with a Trace Heating system to provide frost protection to both the chilled and hot water pipework. 1250m of VC12/2 was used in total.

Thursday 14 February 2008

Walsall Manor Hospital
ESH supplied 400m of FBTBOJ self limited heating tape to this ongoing project.

Tuesday 12 February 2008

Andrew Corporation - USA
Designed and supply 32 x 3.7m dish heater panels designed to fit to the rear of Satellite Receiving Dish Aerials to prevent ice formation.
New Primark - Basingstoke 
The project scope was to supply, install and commission the trace heating system to frost protect the following pipework: 

  • Basement - 40m of ABS chilled water pipework
  • Roof plantroom - 42m of ABS chilled water pipe and 42m of steel heating pipework

Monday 11 February 2008

Holchem Laboratories - Haslingden 
To supply and install type TF trace heating tape to maintain +20°C on the Caustic Pipework.

Friday 8 February 2008

Witney SYW
ESH supplied and installed over 400m of FBTBOJ self regulating heating tape to provide frost protection in the PILS area of the site.

Thursday 7 February 2008

Airedale General Hospital - Keighley 
To supply and install trace heating to the external pipework associated with the San room area and the server room area.

Tuesday 5 February 2008

Huws Care Home - Nottingham 
Supply materials and labour to install and commission the trace heating systems, to provide frost protection to the exposed pipework on the roof and to maintain the DHWS pipework at +55°C. 115m of pipework in total.

Tuesday 29 January 2008

Kingspan Insulation Ltd - Leeds
Supplied materials and labour to install and commission a trace heating system to maintain a temperature of +25°C on 4" & 5" pipework.

Friday 25 January 2008

Cotton Valley STW - Milton Keynes
For this project ESH supplied and installed trace heating to three condensate pots in a Zone 1 Class T3 Gas Group IIB Hazordous Area.

Tuesday 22 January 2008

Cadbury - Bournville 
ESH were contracted to supplied and installed a temperature maintenance system to the HWS pipework during the dining refurbishments.

Monday 21 January 2008

Kings Lynn STW - Norfolk 
Supplied and installed trace heating to provide frost protection to 210m of condensate pipework.

Friday 18 January 2008

Tessenderlo Fine Chemicals Ltd - Leek
ESH supplied 210m of type SCBX (ATEX approved constant wattage heating tape) for the use on two large tanks and associated pipework.

Thursday 17 January 2008

Merchants Academy - Bristol
ESH were contracted to supply and install frost protection to the external pipework as well as to temperature maintain the HWS pipework at +55°C.

Wednesday 16 January 2008

Synthite Ltd - Mold Clwyd
To supply and install trace heating to 90m of steel pipework carrying 37% formalin. The pipework and fittings needed to maintain a temperature of +25°C.

Monday 14 January 2008

RAF Menwith Hill - Harrogate
Supplied and installed a frost protection trace heating system to 1, 2, 3, 6, 8 and 10 inch pipework, totalling 130m.

Tuesday 8 January 2008

Jakemans (Confectioners) Ltd - Boston
Supplied materials only to maintain the temperature of 2" stainless steel pipework at +40°C.