Wednesday, 18 June 2008

Netstore Plc - Reading
For this project ESH were contracted to supply materials and labour to install a trace heating system to frost protect 1500mm NB pipework.

Tuesday, 17 June 2008

Burnley WWTW
ESH supplied and installed an additional 90m of type FBTBOJ self limiting tape to this ongoing project.

Wednesday, 11 June 2008

Tessenderlo Fine Chemicals Ltd - Leek
Designed and supplied a trace heating system to be applied onto a tank 2.95m Ø x 2.1m high, in a Zone 1 Gas Group 11b Classification T3 electrically Hazardous Environment.

Monday, 9 June 2008

Oasis Academy - Immingham
1600m of type H2OWAT55 self regulating heating tape was supplied, installed and commissioned to maintain the DHWS pipework at +55°C.

Thursday, 5 June 2008

Boots Opticians - Higher Chelmer Shopping Centre
ESH supplied and installed 75m of H2OWAT55 to temperature maintain the HWS pipework at 55°C.

Tuesday, 3 June 2008

University Of Sheffield - Music Practice Facility
The scope of work was to design, supply and install a trace heating system to maintain the DHWS pipework temperature at +55°C and periodically purge the system to a temperature of 65°C.

Monday, 2 June 2008

Audi Showroom - Sheffield 
162m of pipework in the basement area was trace heated to provide frost protection in a minimum ambient temperature of -15°C. ESH supplied and installed type VC constant wattage heating tape.