Direct Table Foods - Bury St Edmunds
Supplied additional materials and labour to rearrange and extend the original trace heating system.
TK Maxx Store - Humberstone Gate
ESH supplied and installed the hot water trace heating system to be maintained at +55°C. All pipework was indoors and fitted with our H2OWAT55 self limited heating tape.
Motney Hill STW - Kent
Supply only, 150m of FBT self regulating trace heating tape.
Kings Lynn STW - Norfolk
ESH were contracted to supply and install an additional 306m of VC constant wattage heating tape to vairous different pipeworks within this site.
Banwell WTW
Supplied materials and labour to install and commission trace heating to frost protect the following areas:
- Membrane building area
- PAC/Sulphuric acid area
- Phosphoric acid area
- Booster pump kiosk
Marks & Spencer Stores
ESH supplied and installed two new M&S stores - Luton Arndale Centre & White City London, with a Trace Heating system to provide frost protection to both the chilled and hot water pipework. 1250m of VC12/2 was used in total.
Walsall Manor Hospital
ESH supplied 400m of FBTBOJ self limited heating tape to this ongoing project.
Andrew Corporation - USA
Designed and supply 32 x 3.7m dish heater panels designed to fit to the rear of Satellite Receiving Dish Aerials to prevent ice formation.
New Primark - Basingstoke
The project scope was to supply, install and commission the trace heating system to frost protect the following pipework:
- Basement - 40m of ABS chilled water pipework
- Roof plantroom - 42m of ABS chilled water pipe and 42m of steel heating pipework
Holchem Laboratories - Haslingden
To supply and install type TF trace heating tape to maintain +20°C on the Caustic Pipework.
Witney SYW
ESH supplied and installed over 400m of FBTBOJ self regulating heating tape to provide frost protection in the PILS area of the site.
Airedale General Hospital - Keighley
To supply and install trace heating to the external pipework associated with the San room area and the server room area.
Huws Care Home - Nottingham
Supply materials and labour to install and commission the trace heating systems, to provide frost protection to the exposed pipework on the roof and to maintain the DHWS pipework at +55°C. 115m of pipework in total.